Exact and approximate methods for parallel multiple-area spatial scheduling with release times

  • Regular Article
  • Published:
OR Spectrum Aims and scope Submit manuscript

Abstract

Spatial scheduling problems involve scheduling jobs that each require certain amounts of two-dimensional space within a processing area of limited width and length. Thus, this requires not only assigning time slots to each job but also locations and orientations within the limited physical processing space as well. Such problems, often encountered in shipbuilding and aircraft manufacturing, are generally difficult to solve, and there is a relatively small amount of literature addressing these problems compared to other types of scheduling. In this paper, we consider a particularly complex class of spatial scheduling problems that involve scheduling each job into one of several possible processing areas in parallel to minimize the total amount of tardy time. In addition, each job has a release time before which it may not be processed. We introduce two methods for solving this type of problem: an integer programming (IP) model and a heuristic algorithm. We perform computational tests and comparisons of each method over a large number of generated benchmark problems with varying characteristics, and also compare these to a more naïve heuristic. Solving the IP model was effective for small problems but required excessive amounts of time for larger ones. The heuristic was effective and produced solutions of comparable quality to the IP model for many problems while requiring very little computational time.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  • Aranout JP, Rabadi G, Musa R (2010) A two-stage ant colony optimization algorithm to minimize the makespan on unrelated parallel machines with sequence-dependent setup times. J Intell Manuf 21: 693–701

    Article  Google Scholar 

  • Baker BS, Coffman EG, Rivest RL (1980) Orthogonal packings in two dimensions. SIAM J Comput 9: 846–855

    Article  Google Scholar 

  • Chen CS, Lee SM, Shen QS (1995) An analytical model for the container loading problem. Eur J Oper Res 80: 68–76

    Article  Google Scholar 

  • Cho KK, Chung KH, Park C, Park JC, Kim HS (2001) A spatial scheduling system for block painting process in shipbuilding. CIRP Ann Manuf Technol 50: 339–342

    Article  Google Scholar 

  • Duin CW, Van Sluis E (2006) On the complexity of adjacent resource scheduling. J Schedul 9: 49–62

    Article  Google Scholar 

  • Fleszar K, Charalambous C, Hindi KS (2012) A variable neighborhood descent heuristic for the problem of makespan minimisation on unrelated parallel machines with setup times. J Intell Manuf (In Press)

  • Garcia C, Rabadi G (2009) An optimization model for scheduling problems with two-dimensional spatial resource constraints. In: Proceedings of Modeling and Simulation (MODSIM) World Conference (2009) Virginia Beach

  • Hopper E, Torton BCH (2001) An empirical investigation on metaheuristic and heuristic algorithms for a 2D packing problem. Eur J Oper Res 128: 34–57

    Article  Google Scholar 

  • Hurink JL, Kok AL, Paulus JJ, Schutten JMJ (2011) Time-constrained project scheduling with adjacent resources. Comput Oper Res 38: 310–319

    Article  Google Scholar 

  • Lee KJ, Lee JK (1996) A spatial scheduling system and its application to shipbuilding: DAS-Curve. Expert Syst Appl 10: 311–324

    Article  Google Scholar 

  • Montgomery DC (2001) Design and analysis of experiments. Wiley, New York

    Google Scholar 

  • Padberg M (2000) Packing small boxes into a big box. Math Methods Oper Res 52: 1–21

    Article  Google Scholar 

  • Paulus JJ, Hurink J (2006) Adjacent resource scheduling: why spatial resources are so hard to incorporate. Electron Notes Discrete Math 25: 113–116

    Article  Google Scholar 

  • Pinedo M (2008) Scheduling theory, algorithms and systems, 2nd edn. Springer, New York

    Google Scholar 

  • Rabadi G, Moraga R, Al-Salem A (2006) Heuristics for the unrelated parallel machine scheduling problem with setup times. J Intell Manuf 17: 85–97

    Article  Google Scholar 

  • Ruby (2010) http://www.ruby-lang.org/en, the Ruby language web site

  • Scheduling Research (2005) http://www.schedulingresearch.com, a web site that includes benchmark problems data sets and solutions for scheduling problems

  • Silberschats A, Galvin PB, Gagne G (2009) Operating system concepts, 8th edn. Wiley, New York

    Google Scholar 

  • Varghese R, Yoon, DY (2005) Spatial block arrangement in shipbuilding industry using genetic algorithm for obtaining solution for anticipated bottleneck. In: Proceedings of the fifteenth international offshore and polar engineering conference, vol 4, pp 774–780

  • Weng M, Lu J, Ren H (2001) Unrelated parallel machine scheduling with setup consideration and a total weighted completion time objective. Int J Prod Econ 70: 215–226

    Article  Google Scholar 

  • Yu W, Li W, Goh M, de Souza R (2010) Three-dimensional bin-packing problem with variable bin height. Eur J Oper Res 202: 347–355

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Ghaith Rabadi.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Garcia, C., Rabadi, G. Exact and approximate methods for parallel multiple-area spatial scheduling with release times. OR Spectrum 35, 639–657 (2013). https://doi.org/10.1007/s00291-012-0301-8

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s00291-012-0301-8

Keywords

Navigation