A two-stage stochastic programming approach for project planning with uncertain activity durations

  • Published:
Journal of Scheduling Aims and scope Submit manuscript

Abstract

This paper investigates the problem of setting target finish times (due dates) for project activities with random durations. Using two-stage integer linear stochastic programming, target times are determined in the first stage followed by the development of a detailed project schedule in the second stage. The objective is to balance (1) the cost of project completion as a function of activity target times with (2) the expected penalty incurred by deviating from the specified values. It is shown that the results may be significantly different when deviations are considered, compared to when activities are scheduled as early as possible in the traditional way. For example, the optimal target completion time for a project may be greater than the makespan of the early-start schedules under any scenario. To find solutions, an exact algorithm is developed for the case without a budget constraint and is used as a part of a heuristic when crashing is permitted. All computational procedures are demonstrated on a set of 150 benchmark problems consisting of 90 activities each.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  • Adlakha, V. G., & Kulkarni, V. G. (1989). A classified bibliography of research on stochastic PERT networks. INFOR, 27(3), 272–296.

    Google Scholar 

  • Baker, K. R., & Scudder, G. D. (1990). Sequencing with earliness and tardiness penalties: a review. Operations Research, 38(1), 22–36.

    Google Scholar 

  • Birge, J. R. (1997). Stochastic programming computation and applications. INFORMS Journal of Computing, 9(2), 111–133.

    Google Scholar 

  • Bottcher, J., Drexl, A., Kolisch, R., & Salewski, F. (1999). Project scheduling under partially renewable resource constraints. Management Science, 45(4), 543–559.

    Google Scholar 

  • Buss, A. H., & Rosenblatt, M. J. (1997). Activity delay in stochastic project networks. Operations Research, 45(1), 126–139.

    Google Scholar 

  • Chapman, C. (1997). Project risk analysis and management—PARM the generic process. International Journal of Project Management, 15(5), 273–281.

    Article  Google Scholar 

  • Chrétienne, P., & Sourd, F. (2003). PERT scheduling with convex cost functions. Theoretical Computer Science, 292(1), 145–164.

    Article  Google Scholar 

  • Clausen, J., Hansen, J., Larsen, J., & Larsen, A. (2001). Disruption management. ORMS Today, 28(5), 40–43.

    Google Scholar 

  • Davenport, A. J., & Beck, J. C. (2000). A survey of techniques for scheduling under uncertainty. Unpublished manuscript, Toronto, Canada. Available at http://www.mie.utoronto.ca/staff/profiles/beck/publications.html

  • Elmaghraby, S. E., Ferreira, A. A., & Tavares, L. V. (2000). Optimal start times under stochastic activity durations. International Journal of Production Economics, 64(1–3), 153–164.

    Article  Google Scholar 

  • Goldberg, A. V. (1997). An efficient implementation of a scaling minimum-cost flow algorithm. Journal of Algorithms, 22(1), 1–29.

    Article  Google Scholar 

  • Herroelen, W., & Leus, R. (2004a). The construction of stable project baseline schedules. European Journal of Operational Research, 156(3), 550–565.

    Article  Google Scholar 

  • Herroelen, W., & Leus, R. (2004b). Robust and reactive project scheduling: A review and classification of procedures. International Journal of Production Research, 42(8), 1599–1620.

    Article  Google Scholar 

  • Herroelen, W., De Reyck, B., & Demeulemeester, E. (1998). Resource-constrained project scheduling: A survey of recent developments. Computers & Operations Research, 25(4), 279–302.

    Article  Google Scholar 

  • ILOG (2002). CPLEX 7.5, Reference Manual. ILOG, Inc, Mountain View, CA.

  • Klein Haneveld, W. K., & van der Vlerk, M. H. (1999). Stochastic integer programming: General models and algorithms. Annals of Operations Research, 85, 39–57.

    Article  Google Scholar 

  • Kolisch, R., & Padman, R. (2001). An integrated survey of deterministic project scheduling. Omega, 29(3), 249–272.

    Article  Google Scholar 

  • Kolisch, R., Sprecher, A., & Drexl, A. (1995). Characterization and generation of a general class of resource-constrained project scheduling problems. Management Science, 41(10), 1693–1703. Online library PSPLIB available at http://www.bwl.uni-kiel.de/Prod/psplib/

    Article  Google Scholar 

  • Kouvelis, P., & Yu, G. (1997). Robust discrete optimization and its application. Norwell: Kluwer Academic.

    Google Scholar 

  • Miller, R., & Lessard, D. (2001). Understanding and managing risks in large engineering projects. International Journal of Project Management, 19(8), 437–443.

    Article  Google Scholar 

  • Nemhauser, G., & Wolsey, L. (1988). Integer and combinatorial optimization. New York: Wiley.

    Google Scholar 

  • Pich, M. T., Loch, C. H., & De Meyer, A. (2002). On uncertainty, ambiguity, and complexity in project management. Management Science, 48(8), 1008–1023.

    Article  Google Scholar 

  • Porteus, E. L. (1990). Stochastic inventory theory. In: D.P. Heyman M.J. Sobel (Eds.), Handbooks in operations research and management science: Vol. 2. Stochastic models. Amsterdam: North-Holland.

    Google Scholar 

  • Sourd, F., & Kedad-Sidhoum, S. (2003). The one-machine problem with earliness and tardiness penalties. Journal of Scheduling, 6(6), 533–549.

    Article  Google Scholar 

  • Vanhoucke, M., Demeulemeester, E., & Herroelen, W. (2001). An exact procedure for the resource-constrained weighted earliness—tardiness project scheduling problem. Annals of Operations Research, 102(1–4), 179–196.

    Article  Google Scholar 

  • Van Mieghem, J. A. (2003). Capacity management, investment, and hedging: review and recent developments. Manufacturing & Service Operations Management, 5(4), 269–302.

    Article  Google Scholar 

  • Yang, K.-K. (1996). Effects of erroneous estimation of activity durations on scheduling and dispatching a single project. Decision Sciences, 27(2), 255–290.

    Google Scholar 

  • Yu, G., & Qi, X. (2004). Disruption management: framework, models and applications. Singapore: Word Scientific.

    Google Scholar 

  • Yu, G., Argüello, M., Song, G., McCowan, S. M., & White, A. (2003). A new era for crew recovery at continental airlines. Interfaces, 33(1), 5–22.

    Article  Google Scholar 

  • Zhu, G., Bard, J. F., & Yu, G. (2005). Disruption management for resource-constraint project scheduling. Journal of the Operational Research Society, 56, 365–381.

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Jonathan F. Bard.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Zhu, G., Bard, J.F. & Yu, G. A two-stage stochastic programming approach for project planning with uncertain activity durations. J Sched 10, 167–180 (2007). https://doi.org/10.1007/s10951-007-0008-x

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s10951-007-0008-x

Keywords

Navigation