Process Control in metallurgical plants—From an Xstrata1 perspective

https://doi.org/10.1016/j.arcontrol.2007.08.005Get rights and content

Abstract

Some history and modern practice of Process Control in metallurgical operations is reviewed. Clearly the early deliverables from the pioneer days in the 1950s through to the 1970s and early 1980s were under-appreciated. The discipline has since grown into a more visible, sophisticated and accepted practice as a result of the assembly of appropriately recruited and trained individuals and teams, who have successfully negotiated deliverable projects that impact all metallurgical performances beyond early milling processes. The skill set in these individuals and teams essentially includes organisational behaviour in addition to their specialist technical attributes. A strong network to internal and external specialists and experts is essential. Furthermore, instrumentation and control technology has improved immensely. The challenge in the current modern practice is to win support of senior management in operations for the project cost, schedule and deliverables of Process Control. Once gained, this acceptance then amounts to the logistics of project scope and delivery—a track record well-demonstrated by the Xstrata Process Control Group.

Introduction

The objective of the third plenary lecture is to present the state of the art of applied automatic control and information processing in one or several MMM fields (physical metallurgy, mineral processing, extractive metallurgy, and mining). Mineral processing and extractive metallurgy are the selected MMM fields for this discussion.

In this paper, automation is understood in a broad sense including: measurement and instrumentation; process modelling and simulation; process monitoring and data reconciliation; data mining and multivariate statistics; fault diagnosis and fault tolerant control; Process Control; monitoring of product quality and control performance; off-line and on-line process optimisation; maintenance scheduling and production planning; as well as AI methods like: expert systems, neural networks, fuzzy control.

To address as many of these areas of automation as possible, this paper divides into the following sections:

  • 1.

    Introduction and Process Control definition, objective and cycle

  • 2.

    Elements necessary for successful Process Control in mineral and metallurgical plants, covering:

    • 2.1.

      People—control/process knowledge

    • 2.2.

      Tools—instruments; systems; technology

    • 2.3.

      Actions—support, management, technology transfer

  • 3.

    XPS Process Control philosophy summary

  • 4.

    The ‘near term’ outlook

  • 5.

    Conclusions

Examples and case studies are briefly presented throughout the paper to illustrate the points being made. Acknowledgements and references follow after the conclusions section.

McKee (1999) states:

“Process control is a broad term which often means different things to different people. For the purposes of this (AMIRA) review, process control is considered as the technology required to obtain information in real time on process behaviour and then use that information to manipulate process variables with the objective of improving the metallurgical performance of the plant. This was, in fact, the objective of the early (metallurgical) control systems.”

Furthermore, he goes on to state:
  • “Process Control is a long-established technology.”

  • “Within the minerals industry, single loop pneumatic controllers became commonplace in the 1950s.”

  • “By the mid 1960's, process control was seen by the mineral industry as a technology which offered a great deal in terms of potential improved plant performance.”

  • “Work on flotation control systems began in the early 1970's based upon the availability of on-stream analysis data.”

  • “Although the flotation control task was inherently more difficult than for grinding, there were many promising flotation control systems around the world in the mid to late 70's” (and early 80's).

“Thus, all the elements necessary for successful process control in mineral plants were known and largely available (over) 20 years ago, and were:

  • Instrumentation

  • Control hardware and software

  • A growing understanding of process behaviour and dynamics

  • Operator interfaces providing communication between operator, the system and the process

  • An understanding for the absolute necessity for good instrument maintenance and the capability to perform it

  • An understanding of the need for skilled personnel to develop/maintain control systems

  • Proven successes of many systems

  • Enthusiastic support of management for process control

  • The active and productive involvement of research groups working with enthusiastic operations personnel.”

Although it is now several years later, these key elements have been selected to be discussed in this paper, as they are also seen to be very relevant to the approach of the XPS Process Control Group.

The goal of the XPS Process Control Group is plant Process Control for Operational Performance Excellence. The key elements to achieve this are summarised and addressed in Section 2, under the following sub sections:

  • 2.1

    People—control/process knowledge

  • 2.2

    Tools—instruments, systems, technology

  • 2.3

    Actions—support, management, technology transfer.

More recently, Thwaites and Løkling (2002) stated: “Installed instrumentation calibrated properly with appropriate resolution deadbands, and first order filters, is the basis for good proportional, integral and derivative (PID) control. This offers great potential to plants in reducing variability, opening up opportunities for optimisation through increased throughputs or reduced consumables (e.g. power, steel, reagents, etc.). Tools like Expert systems, Model Predictive Control (MPC) Multivariable controls (MVC) with LP (linear program) optimisers, and even “higher-level” (cascade) PID controllers working on analyser information, provide the means to accomplish significant returns, but these are all dependent on a good/reliable instrumentation base and robust regulatory control.” Fig. 1 is a general diagram, used for many years, to illustrate the overall Process Control objective for any key variable. Measure and understand the initial variability, stabilise and then optimise to the constraint of the process. Typically throughput benefits will come from an increase in the setpoint, and consumable savings will come from a decrease in the setpoint. Once these have been achieved it is important to ‘maintain the gain’ by ensuring the changes are robust, thus benefiting the plant.

In the process of stabilisation, it is very important to consider ‘the whole loop.’ ABB (Forsman, 1998) illustrated this very well, as shown in Fig. 2. Are there any loops in manual? There can be several reasons why controllers are in manual, for example: instrumentation; tuning; operator training; saturation and ability of control actions to influence the control variable, etc. Utilising tools like ExperTune (in 1999, selected by Control Engineering as one of the best products of the year), at the commissioning stage, helps to identify the key issues preventing robust loop control.

Fig. 3 illustrates the critical mill bearing pressure measurements which required a basic filter so that the data is usable for control and better represents the real process issue. For sometime, following plant commissioning, all process signals were unnecessarily ‘noisy’ and it was not surprising that much of the plant's control was manual! Alarming in this plant was also ineffective and poorly commissioned.

Additionally, Process Metallurgists/Engineers also need to be aware of ‘data compaction’ in the production management information system (PMIS). Over compaction, as over filtering, minimises the ability to ‘see’ the real process dynamic response. The XPS Process Control Group is often requesting less compaction, while the IT support is often interested in maximum (and default) compaction. Similarly, PMIS systems should also, but often do not, capture important setpoints and outputs.

Referring back to Fig. 1 then, Process Control objectives can therefore be summarised as the management of tools and resources to: minimise process variation; optimise process performance; minimise (variable) costs; control product quality; and maximise safety.

In general a well established hierarchy (Jones, 1994/1996), as shown in Fig. 4, is followed. Economic returns considerably increase beyond loop regulatory control.

While process and area optimisation can have considerable financial returns, it is well recognised (and reported), by those practising Process Control, that this can only be achieved by having a robust and solid regulatory lower level.

McKee (1999) states:

“Svedala (metso minerals) advocate a systematic approach to process control:

  • start by defining what is important through an analysis of the process (an audit) to determine what is required and the level of control;

  • understand the process and ensure the basics for good control are in place (e.g. instrumentation);

  • match the installed system to the capability of the people available;

  • recognize the on-going commitment required for success;

  • with regard to the actual control, consider three levels as follows:

    • basic PID—via DCS or equivalent;

    • supervisory (cascade control, dead-time compensation, etc.—via DCS or equivalent);

    • optimising (e.g. expert system, adaptive)—via a package such as G2 or implemented within the DCS.”

However, it is important to understand that Process Control will not correct inherent design, instrumentation related flowsheet, and actual flowsheet problems in a plant.

There is a need to determine, and if necessary correct, the condition of the plant as a pre-requisite to control development. A good example is the importance of classifier operation and its effect on comminution circuit performance. Techniques exist (plant sampling, modelling and simulation) to audit the actual plant operation. Correcting plant limitations should be seen as a first step in the control approach.’ (McKee, 1999)

The hybrid Process Mineralogy group at XPS was started up in 1997. The key deliverable from this young discipline is to reliably formulate and demonstrate the optimum flowsheet for the processing of a given ore body (Lotter et al., 2002, Lotter et al., 2003). This hybrid approach of sampling and statistics, geology, mineralogy and mineral processing (Fig. 5) outperforms conventional mineral processing because it describes the flowsheet in terms of representative sampling and minerals instead of assays. Ongoing improvement in the concentrator operations, for example by Process Control projects that reduce variance, is thereafter benchmarked with Statistical Benchmark Surveying. The Process Control is easier to implement when a concentrator operation is on a Process Mineralogy platform, because the flowsheet allows for more responsive controls.

“A good implementation requires a well defined operating philosophy and an associated control strategy.” (McKee, 1999)

The XPS Process Control Group continually make the point that Process Control involvement during the early engineering stages (of a project) ensures effective start-up and the fastest turn-around to on-line process optimisation. Fig. 6 shows the Group's ‘effective Process Control cycle’. This also fits in well with the Company's (Xstrata Copper Canada) Six Sigma stage gate process (also shown in Fig. 6).

The Kidd Metallurgical Site Montcalm project was taken through the full Six Sigma stage gate procedure, ensuring all specified design criteria were met before proceeding to the next stage. This required the Process Control plan (Gillis & Lacombe, 2002) to be developed very early on in the process. Piping and Instrument Drawings (P&IDs) were first developed during 2002 and a detailed Process Control philosophy was written up as well. This philosophy detailed every loop, the expected flows, setpoints, operating ranges, limits, alarms, interlocks, etc.

The control philosophy generally specified only lower level (regulatory) loops with some cascade loops included where necessary. The approach taken was to have the regulatory loops ready for use at circuit start-up and to develop higher-level controls later as required. Following commissioning all control loops had been inspected, optimised and documented with the ExperTune software package, thus allowing the Process Engineers and Operators to focus on optimum process beneficiation, i.e. Operational Performance Excellence.

The XPS Process Control Group are often called into Plant processes after start-up to ‘correct and fix’ poorly commissioned process controls, sometimes after a considerable time period following the new process commissioning.

Fig. 7 shows a recently modified SAG circuit (after several millions of dollars of capital investment) showing a tremendous variability of the feed tonnage (lower trend; S.D. of 9.7 tph on an average of 131 tph) and bearing pressure—indicating ‘mill load’ (upper trend; S.D. of 24 kPa on an average of 4454 kPa) following ‘commissioning’ of the new equipment and few basic controls. Needless to say, this ‘fundamental and critical control’ affecting the whole mill, was soon switched to ‘manual’ placing onus on the operator to maintain mill throughput while not exceeding any of the equipment constraints! Much of the operators’ time was then consumed with this task.

“In grinding, control of AG/SAG mill circuits is the dominant area. While some systems have emerged which provide a reasonable level of control, there is still much not understood about the dynamic behaviour of these mills, and there is considerable scope for further development.” (McKee, 1999)3

Section snippets

Elements necessary for successful Process Control in mineral and metallurgical plants

This section discusses the elements necessary for successful Process Control in mineral and metallurgical plants and what is required to attain operational performance excellence.

Thwaites (1993), Flintoff and Mular (1992) and McKee (1999), as illustrated in Fig. 8, show that successful Process Control is more than the tools—the sensors, PLC/DCS, control software, process information, etc.

It has been the experience of the XPS Process Control Group, that successful Process Control results from a

XPS Process Control philosophy summary

Two of the four business groups at the Xstrata Process Support Centre, the Process Mineralogy Group and the Extractive Metallurgy Group, operate pilot facilities (Fig. 22) that cover milling and flotation processes, as well as hydrometallurgical and pyrometallurgical processes. These are excellent facilities to utilise ‘state of the art’ instrumentation, like Coriolis meters, as well as fieldbus technology (e.g. PROFIBUS), thin client MMI systems together with integrated controls (mostly with

The ‘near term’ outlook

Instrumentation is so much better than it was 25 years ago and procurement agreements with key, major suppliers allows the latest technology into the plants where they are ultimately proven for both accuracy and robustness. Utilisation of ‘asset management’ systems (like E&H's FieldCare) will help to ensure instrumentation is performing appropriately. But this is also where other tools, like PlantTriage (ExperTune Inc.) and online PCA/PLS models (MonitorMV, Perceptive Engineering) can play an

Conclusions

Konigsman (1992): “process control is now an essential part of any concentrator operation. It provides a proven vehicle for improving operation economics by increasing revenues and reducing costs. A substantial number of Canada's mineral processing plants have incorporated this technology, and most have realized impressive returns on investment. The question one must ask is whether we are tapping the full potential of this technology. It is the opinion of the MITEC Mineral Processing Technical

Acknowledgements

The author acknowledges the inspiration provided by Don McKee, through the AMIRA P9L final report. (D. McKee spent 10 years developing control systems, first at Mount Isa, then Climax Molybdenum in Colorado; he is now a Director of the Sustainable Mineral Institute, SMI, University of Qld). The author would also like to thank XPS Management for permission to present/publish this material and all present/past members of the Xstrata Process Control Group whom have contributed in many ways to the

Philip Thwaites (P Eng), is currently employed with Xstrata and is the Manager of Process Control at the Xstrata Process Support Centre (formerly Falconbridge Technology Centre) based in Sudbury, Ontario, Canada. Philip has been working in the mineral processing and metallurgical industry for over 26 years, championing and applying improved Process Control for operational performance excellence. Philip graduated in 1980 from the Royal School of Mines, Imperial College University, London, U.K.

References (32)

  • N.O. Lotter et al.

    Sampling and flotation testing of Sudbury basin drill core for process mineralogy modelling

    Minerals Engineering

    (2003, September)
  • Akzo Nobel Flotation, DEPRAMIN gangue depressants website...
  • M. Bakker et al.

    Growth and acceptance of the ISASMELT process

    CIM Mag.

    (2007, March/April)
  • Bartsch, E. (2006/2007). Raglan SAG charge controller. Grinding Control Update 1 of 2007. Internal presentation and...
  • EFA Technologies Inc. (2002). ‘LeakNet’ fault detection...
  • B. Flintoff et al.

    A practical guide to process controls in the minerals industry

    (1992)
  • K. Forsman

    Control System Performance Monitoring and Optimization, Kostnadseffektiv Drift Ved Hjelp Av Prosesstyring (Effective Plant Costs with help from Process Control)

    (1998, November)
  • Gillis, J. (2000). Flotation control review. Internal...
  • Gillis, J., & Lacombe, P. (2002). Montcalm process control philosophy. Internal...
  • L. Gordon

    Select the best process control. Choosing between PID and model predictive control depends on understanding your process and all its interactions

    Control Engineering

    (2007, January)
  • Jones, R. (1994/1996). What is process control? An introductory guided tour. Plant-Wide Control and Real-Time Process...
  • M. King

    The evolution of technology for extractive metallurgy over the last 50 years—is the best yet to come?

    JOM

    (2007)
  • Koehler, T. (2001). Lakeside best practices in regulatory process control. Course training, Lakeside Process...
  • Konigsman, K. (1992). Foreword—A Practical Guide to Process Controls in the Minerals Industry. Book reference: A...
  • N.O. Lotter et al.

    The development of process mineralogy at Falconbridge Limited, and application to the Raglan Mill

    CIM Bull.

    (2002)
  • D. Lovett et al.

    Automatic control development for the Falcondo ferronickel electric arc furnace

  • Cited by (23)

    • Engineers training in automation of flotation processes

      2014, IFAC Proceedings Volumes (IFAC-PapersOnline)
    View all citing articles on Scopus

    Philip Thwaites (P Eng), is currently employed with Xstrata and is the Manager of Process Control at the Xstrata Process Support Centre (formerly Falconbridge Technology Centre) based in Sudbury, Ontario, Canada. Philip has been working in the mineral processing and metallurgical industry for over 26 years, championing and applying improved Process Control for operational performance excellence. Philip graduated in 1980 from the Royal School of Mines, Imperial College University, London, U.K. with a BSc (engineering) in mineral technology. He started full time engineering work at the Timmins Kidd Creek Mill with Texasgulf in September 1980. Over 16 years, while at Kidd Creek, Philip worked on Process Control optimisation projects and led a Process Control team, also taking on ‘Corporate responsibilities’ associated with Process Control. In 1996 Philip left Timmins, with his family, to continue this work at the Nikkelverk Refinery in Kristiansand, Southern Norway. Focus shifted from copper and zinc Process Control and optimisation to nickel, copper and cobalt. Philip worked at the refinery for 3 years, also learning Norwegian, before returning to Canada, settling in Sudbury in 1999. In 1997 a ‘new’ technology centre, located next to the Falconbridge Nickel Smelter, was completed. On returning to Canada in 1999, Philip has led, and continues to lead, the Process Control Group, a multidisciplinary team, from this ‘state-of-the-art’ centre. The ‘Group’ works in the Company's operating plants and pilot facilities around the world—ensuring metallurgical processes are running efficiently, utilising instrumentation and control.

    Industrial Plenary Lecture: Applications of information processing and automatic control in metallurgical plants.

    1

    Xstrata is a global diversified mining group with its headquarters in Zug, Switzerland. Xstrata's businesses maintain a meaningful position in seven major international commodity markets: copper, coking coal, thermal coal, ferrochrome, nickel, vanadium and zinc, with recycling facilities, additional exposures to gold, cobalt, lead and silver and a suite of global technology products. Xstrata Group's operations and projects span 18 countries: Argentina, Australia, Brazil, Canada, Chile, Colombia, the Dominican Republic, Germany, New Caledonia, Norway, Papua New Guinea, Peru, the Philippines, South Africa, Spain, Tanzania, the USA and the UK. Xstrata employs approximately 43,000 people, including contractors.

    2

    Xstrata Process Support (XPS; previously known as the Metallurgical Technology Group) is an expert group based in Sudbury (Ontario) Canada and at other various Xstrata operating sites. Through the four business areas of: Process Mineralogy, Extractive Metallurgy, Process Control and Materials Technology, XPS provides support to Xstrata commodity businesses, with an objective of providing quality technical expertise for operational support, growth initiatives and strategic development.

    View full text