  • This paper extends the well-known NEH heuristic.

  • The paper introduces new priority rules and decision criteria for the insertion phase.

  • The performance of the proposed 103 heuristics is compared to two well-known heuristics.

  • The proposed heuristics outperform the best known simple heuristic.

Abstract

This paper develops a set of new simple constructive heuristic algorithms to minimize total flow-time for an n-jobs×m-machines permutation flowshop scheduling problem. We first propose a new iterative algorithm based on the best existing simple heuristic algorithm, and then integrate new indicator variables for weighting jobs into this algorithm. We also propose new decision criteria to select the best partial sequence in each iteration of our algorithm. A comprehensive numerical experiment reveals that our modifications and extensions improve the effectiveness of the best existing simple heuristic without affecting its computational efficiency.

Introduction

A flowshop production system is commonly defined as a production system in which a set of n jobs undergoes a series of operations in the same order [23]. Determining optimal job sequences for flowshop scheduling problems can be based on various objectives; minimizing makespan and minimizing total flow-time have, however, most often been considered as objectives for flowshop scheduling problems in the past. The first objective refers to the minimization of the last job's completion time, while the second one aims on minimizing the total in-process time, which reduces work-in-progress inventory [6]. For makespan minimization, problems with more than two machines have been shown to be strongly NP hard [23]; this is even the case for Permutation Flowshop Scheduling Problems, i.e. for flowshop scheduling problems with the same job order on all machines. Garey et al. [11] showed that the problem of minimizing total flow-time with more than one machine belongs to the category of NP complete problems. Accordingly, for large-size problems, heuristic procedures have to be used to find solutions in reasonable computational time. A comprehensive review of research on flowshop scheduling that appeared during the last 50 years is the one of Gupta and Stafford [14]. A review of scheduling problems that aim on minimizing makespan can be found in Ruiz and Maroto [28] and Gupta et al. [13]. The Permutation Flowshop Scheduling Problem with the objective of flow-time minimization was reviewed by Pan and Ruiz [22] and Framinan et al. [8], where the latter also reviewed works that consider makespan minimization. Mutlu and Yagmahan [18] recently reviewed multi-objective flowshop scheduling problems.

Framinan et al. [10] provided a framework to categorize heuristic algorithms for the Permutation Flowshop Scheduling Problem (PFSP) according to their structure. This framework distinguished between the phases of (a) index development, (b) solution construction, and (c) solution improvement. Framinan et al. [9] categorized existing heuristics, which can address one or more of these phases, into two classes: simple and composite heuristics. An algorithm was categorized as a simple heuristic if it does not include another heuristic. Composite heuristics are heuristics that contain at least one simple heuristic for conducting one or more of the three above-mentioned phases. Pan and Ruiz [22] showed that composite heuristics outperform simple heuristics in minimizing flow-time. Yet, as simple heuristics are the basic building blocks of composite heuristics, improving their performance is still of interest for the research community, as this improvement can boost the performance of composite heuristics as well. The aim of this paper is to propose a set of new simple heuristics to improve the performance of the best existing simple heuristic algorithm for minimizing total flow-time in the PFSP.

A popular simple heuristic for minimizing makespan in the general PFSP was presented by Nawaz et al. [19] (we refer to this heuristic as NEH in the following), which outperformed other algorithms developed earlier, such as the heuristics of Palmer [20], Gupta [12], or Campbell et al. [2]. Despite its good performance for makespan-related PFSPs, another advantage of NEH is that it leads to good solutions for other objectives as well, such as minimizing total flow-time (as was shown, for example, by Allahverdi and Aldowaisan [1]). The NEH heuristic consists of two phases, namely (I) the sorting (prioritizing) phase and (II) the insertion phase. In the sorting phase, jobs are sorted in descending order of their total processing time. This sorted list is used in the insertion phase to determine the sequence in which jobs are added to an existing partial sequence. For an n-job PFSP, the insertion phase consists of n iterations. In step k (1kn) of the insertion phase, the kth job on the sorted list is successively assigned to the k possible slots in the current partial sequence that was obtained in the previous iteration, which consists of k1 jobs. The partial sequence that leads to the best value for the objective function (minimum partial makespan) is used as the current k-jobs partial sequence for the next iteration.

Since 1983, many researchers have tried to improve NEH for different objective functions by modifying either its sorting or its insertion phase. One example is the work of Framinan et al. [7], which tried to improve the performance of NEH for three objectives (i.e., makespan, idle time and total flow-time minimization) by applying 177 new ordering policies to the sorting phase of NEH. These policies are combinations of different indicator values and sorting criteria. Most extensions of NEH are more effective than the original version (i.e., they lead to better solutions), but they are usually less efficient (i.e., they are usually more complex and require more computational time than the original NEH).

The relatively high efficiency of NEH is primarily due to the idea of keeping an established partial sequence of a set of jobs unchanged from one iteration until the algorithm terminates. This idea, however, also restricts the effectiveness of NEH, as it does not search for potentially better local solutions once a partial sequence has been established. One option to improve the insertion phase of NEH is to optimize partial sequences by testing alternative positions for jobs at the end of each iteration, i.e. to evaluate the neighborhood of each partial sequence. A similar idea was presented by Rajendran [24], who optimized partial sequences by exchanging adjacent jobs pairwise with the objective to minimize total flow-time. Framinan and Leisten [6] combined this idea with NEH and performed pairwise exchanges at the end of each iteration to improve partial sequences. The authors showed that their algorithm (to which we refer as FL hereafter) outperformed other constructive algorithms for the total flow-time criterion. Framinan et al. [9] evaluated different heuristic algorithms for the PFSP and concluded that the FL heuristic led to better solutions for the total flow-time criterion. Laha and Sarin [17] extended FL by allowing all jobs assigned to a partial sequence to change their respective position by checking all other k1 slots at the end of each iteration. They showed that their algorithm (to which we refer as LS in the following) leads to a better performance, in terms of the quality of the solutions, and only a small loss in efficiency as compared to the FL heuristic. Pan and Ruiz [22] reviewed the most promising constructive heuristics and indicated that LS is the best existing simple heuristic to minimize total flow-time in general PFSPs in terms of the quality of the results. Since LS is computationally complex, the authors developed some new composite heuristics that outperform LS and at the same time consume about one order of magnitude less CPU time. Recently, Fernandez-Viagas and Framinan [5] proposed a set of new constructive heuristics (we refer to them as FF heuristics in the following) and compared them with some of the heuristics considered in Pan and Ruiz [22]. Although some of their composite algorithms showed a better performance than the ones proposed in Pan and Ruiz [22], their proposed simple heuristics (all pure FF heuristics, i.e. FF(1)–FF(n)) are outperformed by LS.

As mentioned above, having promising composite heuristics does not render efforts to improve simple heuristics worthless. Better simple heuristics may open the gate for the development of even better composite heuristics. Based on LS, this paper proposes several new simple heuristics for the PFSP. Numerical experiments illustrate that our modifications lead to a significant improvement in terms of the quality of the solutions without affecting the computational efficiency as compared to the best existing simple heuristic.

The remaining sections of this paper are organized as follows. Section 2 outlines the heuristic of Laha and Sarin [17] and possible modifications for its extensions. Section 3 describes the proposed heuristics in detail. A comprehensive comparison of the proposed heuristics and LS, together with a detailed evaluation of the effect of the proposed modifications on NEH and LS, are given in Section 4, and Section 5 concludes the paper.

Section snippets

The heuristic of Laha and Sarin and its modifications

Both the FL and LS heuristics optimize partial sequences at the end of each iteration of NEH's insertion phase. This paper focuses on improving the LS heuristic, which outperforms all other existing simple heuristics for optimizing total flow-time in a permutation flowshop manufacturing system [22]. The pseudocode of LS is the following:

Step 1: Pi=j=1mpij, i=1,2,,n, where Pi is the indicator value of job i and pij is the processing time of job i on machine j.

Step 2: Sort the jobs in an

AGB (focuses on Option 7 to improve LS)

The sorted list (obtained in Step 2) is used both in the FL and LS heuristics only to determine the order in which jobs are inserted into the partial sequence. The heuristic proposed here uses the priority orders more effectively in the insertion phase; in the following, we refer to this heuristic as AGB. AGB uses the first three steps of LS and then continues as follows:

Step 4: for k=3,,n repeat the following:

  • 4.1 Insert the kth job in all k possible slots in the current partial sequence

Computational experiment

This section examines the performance of the heuristics proposed in Section 3. As mentioned before, Framinan et al. [8] showed that using a modified version of the NEH algorithm with jobs sorted in ascending order leads to better results. Therefore, we compare the results of the heuristics proposed in this paper with the modified version of NEH (named hereafter NEH/Pi/A). We also compared the performance of the newly developed heuristics with the performance of the LS heuristic. In addition, we

Summary and conclusion

The best-known simple constructive heuristics algorithm for optimizing the permutation flowshop scheduling problem with total flow-time as objective, developed by Laha and Sarin [17], was modified in this paper by employing different improvement options, which led to 103 new heuristics. A comprehensive computational experiment was conducted to examine the effects of each modification in detail. One of our metrics for comparing the performance of algorithms showed that our modifications result

References (33)

Cited by (25)

  • Scheduling blocking flowshops with setup times via constraint guided and accelerated local search

    2019, Computers and Operations Research
    Citation Excerpt :

    NEH (Nawaz et al., 1983) is a very well-known greedy constructive heuristic for PFSPs (Ruiz and Maroto, 2005). Because of its effectiveness, there exist a number of variants (Abedinnia et al., 2016; Framinan et al., 2003; Liu et al., 2017) for PFSPs and also for other PFSP variants (Riahi et al., 2017; Wang et al., 2018). NEH has two main steps: ordering jobs initially and then inserting jobs, one by one, into their best positions in the already obtained partial sequences.

  • Minimizing flowtime in a flowshop scheduling problem with a biased random-key genetic algorithm

    2019, Expert Systems with Applications
    Citation Excerpt :

    Such method was improved by Fernandez-Viagas and Framinan (2015), leading to the O(n2m) FF algorithm. Afterward, Abedinnia, Glock, and Brill (2016) and Rossi, Nagano, and Sagawa (2017) described new constructive methods which, despite some potential results on the quality of the solutions, have a higher complexity than FF thus making them inefficient for larger instances. Recently, Fernandez-Viagas and Framinan (2017) proposed a Beam-Search Constructive Heuristic (BSCH) based on the FF method by Fernandez-Viagas and Framinan (2015).

  • Product Scheduling in a Flowshop Cell

    2018, Procedia Manufacturing
  • Enhanced migrating birds optimization algorithm for the permutation flow shop problem with sequence dependent setup times

    2018, European Journal of Operational Research
    Citation Excerpt :

    Ruiz and Maroto (2006) show that the NEH to be the best heuristic, even better than more modern heuristics. Some authors, like Dong, Huang, and Chen (2008), Kalczynski and Kamburowski (2007) or more recently Abedinnia, Glock, and Brill (2016) have shown that some methods improve on the NEH performance. However, the improvement is relatively small, as these methods focus on the ties that occur in the insertion steps of the NEH.