A Neural Network Based Heuristic for Resource-Constrained Project Scheduling

  • Conference paper
Advances in Neural Networks – ISNN 2005 (ISNN 2005)

Part of the book series: Lecture Notes in Computer Science ((LNTCS,volume 3496))

Included in the following conference series:

Abstract

Resource-constrained project scheduling allocates scarce resources over time to perform a set of activities. Priority rule-based heuristics are the most widely used scheduling methods though their performance depends on the characteristics of the projects. To overcome this deficiency, a feed-forward neural network is designed and integrated into the scheduling scheme so as to automatically select the suitable priority rules for each stage of project scheduling. Testing on Patterson’s classic test problems and comparison with other heuristics show that the proposed neural network based heuristic is able to improve the performance of project scheduling.

Project 70401017 is supported by National Natural Science Foundation of China.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 84.99
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 109.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

References

  1. Herroelen, W., de Reyck, B., Demeulemeester, E.: Resource-Constrained Project Scheduling: A Survey of Recent Developments. Comput. Oper. Res. 25, 279–302 (1998)

    Article  MATH  MathSciNet  Google Scholar 

  2. Kolisch, R., Padman, R.: An Integrated Survey of Deterministic Project Scheduling. Omega-Int. J. Manage. Sci. 29, 249–272 (2001)

    Article  Google Scholar 

  3. Kolisch, R.: Serial and Parallel Resource-Constrained Project Scheduling Methods Revisited: Theory and Computation. Eur. J. Oper. Res. 90, 320–333 (1996)

    Article  MATH  Google Scholar 

  4. Alvarez-Valdes, R., Tamarit, J.M.: Heuristic Algorithms for Resource-Constrained Project Scheduling: A Review and an Empirical Analysis. In: Slowinski, R., Weglarz, J. (eds.) Advances in Project Scheduling, pp. 113–134. Elsevier, Amsterdam (1989)

    Google Scholar 

  5. Ulusoy, G., Ozdamar, L.: Heuristic Performance and Network/Resource Characteristics in Resource Constrained Project Scheduling. J. Oper. Res. Soc. 40, 1145–1152 (1989)

    MATH  Google Scholar 

  6. Ash, R.C.: Activity Scheduling in the Dynamic, Multi-Project Setting: Choosing Heuristics through Deterministic Simulation. In: Farrington, P.A., et al. (eds.) Proceedings of the 1999 Winter Simulation Conference, pp. 937–941. ACM Press, New York (1999)

    Google Scholar 

  7. Schirmer, A.: Resource-constrained Project Scheduling: An Evaluation of Adaptive Control Schemes for Parameterized Sampling Heuristics. Int. J. Prod. Res. 39, 1343–1365 (2001)

    Article  MATH  Google Scholar 

  8. Kolisch, R., Sprecher, A., Drexl, A.: Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems. Manage. Sci. 41, 1693–1703 (1995)

    Article  MATH  Google Scholar 

  9. Patterson, J.H.: A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem. Manage. Sci. 30, 854–867 (1984)

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2005 Springer-Verlag Berlin Heidelberg

About this paper

Cite this paper

Shou, Y. (2005). A Neural Network Based Heuristic for Resource-Constrained Project Scheduling. In: Wang, J., Liao, X., Yi, Z. (eds) Advances in Neural Networks – ISNN 2005. ISNN 2005. Lecture Notes in Computer Science, vol 3496. Springer, Berlin, Heidelberg. https://doi.org/10.1007/11427391_127

Download citation

  • DOI: https://doi.org/10.1007/11427391_127

  • Publisher Name: Springer, Berlin, Heidelberg

  • Print ISBN: 978-3-540-25912-1

  • Online ISBN: 978-3-540-32065-4

  • eBook Packages: Computer ScienceComputer Science (R0)

Publish with us

Policies and ethics