Abstract
Resource-constrained project scheduling allocates scarce resources over time to perform a set of activities. Priority rule-based heuristics are the most widely used scheduling methods though their performance depends on the characteristics of the projects. To overcome this deficiency, a feed-forward neural network is designed and integrated into the scheduling scheme so as to automatically select the suitable priority rules for each stage of project scheduling. Testing on Patterson’s classic test problems and comparison with other heuristics show that the proposed neural network based heuristic is able to improve the performance of project scheduling.
Project 70401017 is supported by National Natural Science Foundation of China.
Access this chapter
Tax calculation will be finalised at checkout
Purchases are for personal use only
Preview
Unable to display preview. Download preview PDF.
References
Herroelen, W., de Reyck, B., Demeulemeester, E.: Resource-Constrained Project Scheduling: A Survey of Recent Developments. Comput. Oper. Res. 25, 279–302 (1998)
Kolisch, R., Padman, R.: An Integrated Survey of Deterministic Project Scheduling. Omega-Int. J. Manage. Sci. 29, 249–272 (2001)
Kolisch, R.: Serial and Parallel Resource-Constrained Project Scheduling Methods Revisited: Theory and Computation. Eur. J. Oper. Res. 90, 320–333 (1996)
Alvarez-Valdes, R., Tamarit, J.M.: Heuristic Algorithms for Resource-Constrained Project Scheduling: A Review and an Empirical Analysis. In: Slowinski, R., Weglarz, J. (eds.) Advances in Project Scheduling, pp. 113–134. Elsevier, Amsterdam (1989)
Ulusoy, G., Ozdamar, L.: Heuristic Performance and Network/Resource Characteristics in Resource Constrained Project Scheduling. J. Oper. Res. Soc. 40, 1145–1152 (1989)
Ash, R.C.: Activity Scheduling in the Dynamic, Multi-Project Setting: Choosing Heuristics through Deterministic Simulation. In: Farrington, P.A., et al. (eds.) Proceedings of the 1999 Winter Simulation Conference, pp. 937–941. ACM Press, New York (1999)
Schirmer, A.: Resource-constrained Project Scheduling: An Evaluation of Adaptive Control Schemes for Parameterized Sampling Heuristics. Int. J. Prod. Res. 39, 1343–1365 (2001)
Kolisch, R., Sprecher, A., Drexl, A.: Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems. Manage. Sci. 41, 1693–1703 (1995)
Patterson, J.H.: A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem. Manage. Sci. 30, 854–867 (1984)
Author information
Authors and Affiliations
Editor information
Editors and Affiliations
Rights and permissions
Copyright information
© 2005 Springer-Verlag Berlin Heidelberg
About this paper
Cite this paper
Shou, Y. (2005). A Neural Network Based Heuristic for Resource-Constrained Project Scheduling. In: Wang, J., Liao, X., Yi, Z. (eds) Advances in Neural Networks – ISNN 2005. ISNN 2005. Lecture Notes in Computer Science, vol 3496. Springer, Berlin, Heidelberg. https://doi.org/10.1007/11427391_127
Download citation
DOI: https://doi.org/10.1007/11427391_127
Publisher Name: Springer, Berlin, Heidelberg
Print ISBN: 978-3-540-25912-1
Online ISBN: 978-3-540-32065-4
eBook Packages: Computer ScienceComputer Science (R0)