Abstract
The replacement of air handlers in department stores must be completed within a 12-h time frame outside normal working hours to avoid interrupting business operations. This study employed a work breakdown structure to develop a replacement regime for air handlers. This research has calculated start and finish times of these tasks for conventional and constraint time construction projects, and determined labor distribution for each task according to these times. Gantt charts were used to schedule construction progress and to analyze the increase in crashing costs when a constraint time construction model is employed. The start and finish times of various tasks were calculated for completed example projects. The comparison results were then used to analyze root causes and to formulate related countermeasures. An expert interview was conducted to verify the correctness of the proposed countermeasures. The findings of this study can serve as valuable references in air handler replacement projects.





Similar content being viewed by others
Explore related subjects
Discover the latest articles, news and stories from top researchers in related subjects.References
Pasit Lorterapong, Ussavadilokrit M (2013) Construction scheduling using the constraint satisfaction problem method. J Const Eng Manag 139(4):414–422
Nguyen TQ, Chua DKH (2015) Preemptive Constraint Analysis in Construction Schedules. J Comp Civil Eng 29(5):04014062
Talukhaba AA, Acheampong E, Miruka CO (2010) Improving time management in the South African construction industry. Int J Decision Sci Risk Manag 2(3–4):327–339
Jan SH, Ping HS (2006) Construction project buffer management in scheduling planning and control, 2006 Proceedings of the 23rd International Symposium on Robotics and Automation in Construction. 858–863
Sonmez R, Iranagh MA, Uysal F (2016) Critical sequence crashing heuristic for resource-constrained discrete time-cost trade-off problem. J Const Eng Manag. 142(3):04015090
Tiwari S, Johari S (2015) Project scheduling by integration of time cost trade-off and constrained resource scheduling. J Inst Eng (India) Ser A (Civil Architect Environ Agric Eng) 96(1):37–46
Cheng YS, Cheng H (2014) Concept and application of engineering breakdown structure. China Civil Eng J 47(4):125–130
Maravas A, Pantouvakis JP, Lambropoulos S (2014) An Integrated Information System for Monitoring Construction Works. Int J Info Technol Project Manag 5(1):33–44
Doty S (2011) Energy saving measure interactions in chilled water systems. Energy Eng J Assoc Energy Eng 108(5):7–35
Callari JJ (2010) Well, well, well··· processor taps into novel underground cooling solution. Plastics Technol 56(12):22–24
Central Weather Bureau—Weather Statistics http://www.cwb.gov.tw/V7/climate/monthlyData/mD.htm. Accessed 2016/5/25
Taiwan Refrigeration and Air-Conditioning Engineering Association. Installation Manual for Air Conditioning Engineering. Taipei, 2010
Lorterapong P, Ussavadilokrit M (2013) Construction scheduling using the constraint satisfaction problem method. J Const Eng Manag 139(4):414–422
Liu SS, Wang CJ (2011) Optimizing project selection and scheduling problems with time-dependent resource constraints. Auto Const 20(8):1110–1119
Zhang ZY, Sun LY, Liu JF (2012) Optimization of steel plate cutting stock planning with time constraint. Comp Integrated Manuf Syst 18(9):1938–1947
Yu WD (2013) Practical project management. National Chung Hua University Department of Construction Management, Hsinchu
Author information
Authors and Affiliations
Corresponding author
About this article
Cite this article
Shiau, YC., Chuang, HW., Liu, CC. et al. Study on constraint time construction model for replacement of air handling unit in department stores. Artif Life Robotics 21, 324–331 (2016). https://doi.org/10.1007/s10015-016-0285-6
Received:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s10015-016-0285-6