Abstract
This study deals with component supply planning in assembly systems, i.e. where several types of components are needed to produce one finished product. The actual component lead times have random deviations, so they can be considered as random variables. MRP approach with Periodic Order Quantity policy is considered. The aim is to find the optimal MRP offsetting. The proposed model and algorithms minimize the sum of the setup and average holding costs for the components, while satisfying a desired service level.
Similar content being viewed by others
References
Arda Y., Hennet J. C. (2006) Inventory control in a multi-supplier system. International Journal of Production Economics 104(2): 249–259
Axsäter S. (2005) Planning order release for an assembly system with random operations times. OR Spectrum 27: 459–470
Axsäter S. (2006) Inventory control, 2nd edition. Springer, Berlin
Baker K. R. et al (1993) Requirement planning. In: Graves S. C. (eds) Handbooks in operations research and management science, logistics of production and inventory, vol. 4. North-Holland, Amsterdam, pp 571–628
de Kok T. G., Visschers J. W. C. H. (1999) Analysis of assembly systems with service level constraints. International Journal of Production Economics 59: 313–326
Dolgui A. (2001) On a model of joint control of reserves in automatic control systems of production. Automation and Remote Control 62(12): 2020–2026
Dolgui A., Portmann M. C., Proth J. M. (1995) Planification de systèmes d’assemblage avec approvisionnement aléatoire en composants. Journal of Decision Systems 4(4): 255–279
Dolgui A., Louly M. A. (2002) A model for supply planning under lead time uncertainty. International Journal of Production Economics 78: 145–152
Dolgui A., Prodhon C. (2007) Supply planning under uncertainties in MRP environments: A state of the art. Annual Reviews in Control 31(2): 269–279
Elhafsi M. (2002) Optimal leadtimes planning in serial production systems with earliness and tardiness costs. IIE Transactions 34: 233–243
Fujiwara O., Sedarage D. (1997) An optimal (Q,r) policy for a multipart assembly system under stochastic part procurement lead times. European Journal of Operational Research 100: 550–556
Kaplan R. S. (1970) A dynamic inventory model with stochastic lead times. Management Science 16: 491–507
Khang D. B., Fujiwara O. (1993) Multi-period stochastic network flow problems with service level requirements: approximation and error estimates. IIE Transactions 25(2): 104–110
Koh S. C. L., Saad S. M. (2003) MRP-controlled manufacturing environment disturbed by uncertainty. Robotics and Computer Integrated Manufacturing 19: 157–171
Kumar A. (1989) Component inventory cost in an assembly problem with uncertain supplier lead-times. IIE Transactions 21(2): 112–121
Lee H. L., Nahmias S. et al (1993) Single-product, single-location models. In: Graves S. C. (eds) Handbooks in operations research and management science, logistics of production and inventory, vol. 4. North-Holland, Amsterdam, pp 3–57
Liberatore M. J. (1979) The EOQ model under stochastic lead times. Operations Research 27: 391–396
Louly M. A., Dolgui A. (2002) Newsboy model for supply planning of assembly systems. International Journal of Production Research 40: 4401–4414
Louly M. A., Dolgui A. (2004) The MPS parameterization under lead time uncertainty. International Journal of Production Economics 90: 369–376
Louly M. A., Dolgui A., Hnaien F. (2008a) Supply planning for single-level assembly system with stochastic component delivery times and service level constraint. International Journal of Production Economics 115(1): 236–247
Louly M. A., Dolgui A., Hnaien F. (2008b) Optimal supply planning in MRP environments for assembly systems with random component procurement times. International Journal of Production Research 46(19): 5441–5467
Louly, M.A., & Dolgui, A. (2008). An optimization approach for time phasing in MRP systems. In: Preprints of the fifteen international working seminar on production economics, Innsbruck, Austria, March 3–7, vol. 3, pp. 273–280.
Molinder A. (1997) Joint optimisation of lot-sizes, safety stocks and safety lead times in an MRP system. International Journal of Production Research 35: 983–994
Mula J., Poler R., Garcıa-Sabater J. P., Lario F. C. (2006) Models for production planning under uncertainty: A review. International Journal of Production Economics 103: 271–285
Petruzzi N. C., Dada M. (1999) Pricing and the newsvendor problem: A review with extensions. Operations Research 47: 183–194
Porteus E. L. (1990) Stochastic inventory theory. In: Heyman D. P., Sobel M. J. (eds) Hand-book in OR and MS, vol. 2. Elsevier Science Publishers, Amsterdam, pp 605–652
Proth J. M., Mauroy G., Wardi Y., Chu C., Xie X. (1997) Supply management for cost minimization in assembly systems with random component yield times. Journal of Intelligent Manufacturing 8(5): 385–403
Rao S., Schneller G. O. (1990) On the stochastic non-sequential production-planning problem. Journal of the Operational Research Society 41: 241–247
Rosling K. (1989) Optimal inventory policies for assembly systems under random demands. Operations Research 37: 365–579
Sipper D., Bulfin R. L. Jr. (1998) Production: Planning, control and integration. McGraw Hill, New York
Sridharan V., Berry W. L. (1990) Master production schedule, make-to-stock products: A framework for analysis. International Journal of Production Research 28: 541–558
Sox C. R., Muckstadt J. A. (1996) Multi-item, multi-period production planning with uncertain demand. IIE Transactions 28: 891–900
Tang O., Grubbstrom R. W. (2003) The detailed coordination problem in a two-level assembly system with stochastic lead times. International Journal of Production Economics 81–82: 415–429
Tempelmeier H. (2006) Inventory management in supply networks: Problems, models, solutions. Books on demand GmbH, Germany
Whybark D. C., Wiliams J. G. (1976) Material requirement under uncertainty. Decision Science 7: 595–606
Yano C. A. (1987a) Setting planned leadtimes in serial production systems with tardiness costs. Management Science 33(1): 95–106
Yano C. A. (1987b) Stochastic leadtimes in two-level assembly systems. IIE Transactions 19(4): 95–106
Yeung J. H. Y., Wong W. C. K., Ma L. (1998) Parameters affecting the effectiveness of MRP systems: A review. International Journal of Production Research 36: 313–331
Yeung J. H. Y., Wong W. C. K., Ma L., Law J. S. (1999) MPS with multiple freeze fences in multi-product multi-level MRP systems. International Journal of Production Research 37: 2977–2996
Zipkin P. (2000) Foundation of inventory management. McGraw-Hill, New York
Author information
Authors and Affiliations
Corresponding author
Rights and permissions
About this article
Cite this article
Louly, MA., Dolgui, A. & Al-Ahmari, A. Optimal MRP offsetting for assembly systems with stochastic lead times: POQ policy and service level constraint. J Intell Manuf 23, 2485–2495 (2012). https://doi.org/10.1007/s10845-011-0515-7
Received:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s10845-011-0515-7